We are looking at cooking a product to 90 degree C and then chilling the product to less than 5 degrees C. What is the maximum time allowed for the product to cool down? Typically for other products we cool it down in 4 hours however for this product it takes close to 5-6 hours as the product is quite dense (potatoes) . Are they any legal limits / regulations you can share which allows for more than 5 hours to cool the product down? Many thanks in advance
We are looking at cooking a product to 90 degree C and then chilling the product to less than 5 degrees C. What is the maximum time allowed for the product to cool down? Typically for other products we cool it down in 4 hours however for this product it takes close to 5-6 hours as the product is quite dense (potatoes) . Are they any legal limits / regulations you can share which allows for more than 5 hours to cool the product down? Many thanks in advance
Cooling guidelines for Acid Foods
Frozen meals - cooling requirements
Water Concentration recommended for a cooling bath using Sodium hypochlorite 12.5%
For temperature cooling does the time limit of 2-hour start when the temperature is at 135 °F for the sauce?
Sauce cooling
Product cooling (RTE) in an ingredient storage area
Allergen segregation during cooling ?
Product not reaching the cooling temperature as per the FDA guidance
Cooling Product in Small bakery
Question Regarding Cooling for NRTE