Construction During an Audit

Started by , Sep 24 2024 03:24 PM
3 Replies

Hello, 

 

We have our audit coming up in a couple of weeks and while the audit is going on, we will be in the middle of doing a construction project for a new line that we are adding in. Does anyone have any experience in how to handle an audit during construction? Right now some of the things we have done are; putting up a temporary all that sections off a majority of where the construction is happening from the rest of the warehouse. Since we also have a lot of contractors coming in and out, we have given them red hairnets to wear as a way to identify who is a contractor. Is there something else we should be doing though? Paperwork, risk assessments, management of control, increased swabs, etc?

 

Your guidance is greatly appreciated!

 

Chris 

Share this Topic
Topics you might be interested in
New construction due to Expanding our FSC- Baking Left Construction to Join the Family Business Are there any written standards for construction of new food factory in UK? Construction and layout for a new seafood processing facility Food Safety SOPs Following Construction
[Ad]

Hi Chris,

Make sure your GMP is not compromised, and there are no risks to product safety and quality. Contractors should also be adhering to your company's policies. I don't think increased swabs is required at this time unless you notice something. They should be signing in/out though. 

 

As long as you are making all the efforts to not have your products affected by this construction project, you are good! Keep good documentation always. 

 

Good luck! 

1 Like

Oh what fun. Be certain your "approved service providers" docs are up to speed, that all chemicals, paints. Etc are checked and approved, increase inspections for potential drift and ingress egress areas.

 

Make sure all contractors have been trained on your GMP'S as they pertain to contractors.

 

Outside of that have a no stress audit.

2 Likes

hi ;) 

 

from BRC issue 9 

 

4.3.9

 

Temporary structures constructed during building work or refurbishment etc. shall be designed and located to avoid pest harbourage and ensure the safety and quality of products.
 
Risk assessment of temporary activities or structures should be completed prior to their introduction.
 
risk assessment should consider : 
 
- Contractors training (PPE, equipment, site colour coding rules, allergens, CAYG, food defence, site security etc) 
- location (how far from open product)
- dust (air particles) 
- GMP
- Cleaning 
 ;) 
 
1 Like

Similar Discussion Topics
New construction due to Expanding our FSC- Baking Left Construction to Join the Family Business Are there any written standards for construction of new food factory in UK? Construction and layout for a new seafood processing facility Food Safety SOPs Following Construction Level of access for a contract worker, e.g., construction SQF 11.2.3 Wall Construction What additional steps does a food plant need to take when undergoing construction? 13.2.3.1 Ceilings - durable construction defined Construction - Service Provider who Sub-Contracts